Building Height: 56′
Total Roof Area: 30,079 sq ft
Deck Substrate: Concrete
Vapour Retarder: Existing left in place
Original insulation: 1” fiberboard left in place – soiled/damaged insulation was replaced, as needed
Insulation: 1.5” Polyisocyanurate and 0.5” fiberboard cover board applied in roofing asphalt
Membrane Type: 2-Ply SBS Modified Bitumen membrane with roofing asphalt and granular cap sheet, torch applied.
Ballast: None
Flashings: 2-Ply SBS Modified Bitumen with granular cap sheet grey
Metal Coping: 26 gauge dark brown pre-painted metal
Client Name: Ranee Management (repeat client)
Address: 521-523 Finch Avenue West, Toronto (North York neighborhood)
Project: Roof replacement on a 6-storey Residential Apartment building built in 1960
Timeframe: September 5, 2023 – November 15, 2023
The client was quite concerned about the impact the roof replacement would have on the building’s tenants. We would need to take steps to meet these objectives:
The biggest hurdle was the tight space available at the base of the building for staging and working. The main issue was how to get material delivered to the rooftop.
We would need to tackle the removal of all of the roofing layers plus keep the building watertight while dealing with multiple active leaks we discovered. Removing dry, fully adhered fiberboard insulation is also a difficult process, as the insulation needs to be chipped off in small pieces, potentially causing damage to the vapour retardant and concrete substrate. Other unexpected (and unwelcome surprises) along the way presented additional challenges.
The ballasted EPDM overlay membrane was in extremely poor condition. The membrane was not secured at the perimeters, causing it to shift or move, resulting in large rips and visible leaks. We noted significant EPDM membrane shrinkage from lack of securement at the parapet walls and upturns. In addition, the insulation on the top layer of the roof assembly was completely saturated.
Once we removed the stone ballast, EPDM membrane, and top layer of insulation, the existing original membrane was the only layer providing protection from rain. We had to be very careful to inspect and keep this membrane sealed. At times, this called for some material temporary repairs.
At the commencement of our work it was revealed that the exhaust fan housings were in worse shape than indicated by our original inspection. In addition, the membrane around the fan housing curb upturns was not secured adequately. Leaks caused by these issues meant we would need request that the landlord engage a company to replace the housings to ensure the new roof was watertight. The housings were probably original and over 60 years old!
The removal process revealed that the overlay EPDM membrane had hidden large areas of water ponding, requiring the installation of additional roof drains. There were also 2 layers of roof membrane and insulation on the building making drainage hard to assess until the assembly was installed.
The original parapet walls were too low and combined with the new thicker insulation we added, required modifications.
Several unanticipated challenges required us to coordinate with other trades, including HVAC (York Sheet Metal) and Plumbing (Silver Plumbing).
The Elite team went above and beyond to resolve the multiple issues we encountered during project implementation, without derailing the roof removal or replacement. We successfully met the goal of re-roofing the complex without significant impact on the tenants–even with repeated and unanticipated challenges.
We attribute much of the success to the factors below.
Successfully planning and implementing a residential apartment building roof replacement is a major undertaking under optimal circumstances. So many things can go awry. Our advice for roofers is always to be ready to adapt quickly on the job site without deviating from the ultimate primary goal set at the beginning of the project.
When hiring a roofing contractor, look for one with relevant experience and the technical knowledge to execute the original scope of work plus overcome unexpected challenges. Other characteristics to look for include transparency with clients, project leadership skills, and a commitment to meeting the client’s priorities. Elite Roofing is committed to getting the best results for our clients, aligning with their priorities and meeting whatever challenges come our way.