Roofing for Addition to a Retirement Residence in Toronto Suburb

Roofing for Retirement Residence Addition at a Long-Term Care Medical Facility in Toronto Suburb.

Project Specifications

Project Manager: Avcon Construction
Location: North York, Toronto suburb
Building Type: Medical Complex/Retirement Residence
Construction: New Building Addition

A repeat client awarded us a roofing for a retirement residence project — an addition to a low-rise long-term residence for patients with Alzheimer’s and Dementia. The addition would, in effect, double the facility’s size, and its tiered design required careful planning.

Client Goal/Purpose of Project

Elite Roofing and the project team needed to resolve several challenging situations, and we managed to get through the process while limiting any issues with residents. Through pre-planning and close communication with all involved parties, this complex multi-tier medical facility will soon be ready to serve future residents and their families.

Client Testimonial

“We use Elite Roofing extensively and find them to be very responsive to our roofing needs and concerns, whether it be an emergency leak, or walkthrough.”

Key Challenges

Planning & Execution

Outcome

Pre-planning and Problem-Solving

Elite, the construction manager, engineers, and the client’s team held several pre-start onsite meetings to address issues, find solutions, and ensure a smooth work process and on-time completion. Working together, we overcame the challenges of this complex project.

Roofing Material

Together with the team, we agreed that the best choice of roof membrane for this project would be a 2-ply modified bitumen membrane. Given the flat substrate consisting of hollow-core concrete slabs, 2% fully tapered insulation (with 4% tapered crickets), extensive HVAC equipment and high traffic terrace areas, this choice made the most sense.  This system assembly would accomplish the following:

Stand up against the heavy mechanical rooftop equipment required for roof installation and continued foot traffic.
Reduce slipping in wet weather and icy winter conditions, improving safety for roofers, HVAC, and other trades.
2-ply modified bitumen membrane offers multi-ply redundancy, and therefore offers a better long-term lifespan.

Limited Job Site Size

The job site was relatively tight and given the over 600 pieces of taper insulation delivered to the site, the lack of storage space on the roof for our material, and the HVAC and roofing equipment required for installation. Our mobilization approach was to complete our scope of work in stages. This limited the amount of material needed onsite and optimized the space for material delivery, accessibility, and mobilization.

Our 4-Stage Approach

  1. Install the fully adhered modified bitumen vapour retarder to make the structure water-tight from the start.
  2. Install all insulation layers and only the base sheet of the 2-ply modified bitumen membrane.
  3. Install the cap sheet, completing the roof membrane installation.
  4. After the exterior façade and windows are in place, we will return to measure and install metal copings, as needed.

Flat Surface for Tapered Insulation

Tapered insulation must be installed on a totally flat substrate surface for accurate installation and top performance, including drainage. However, the hollow-core concrete slabs form undulations where the slabs join together. We needed to determine how to best create an even surface.

The team agreed that the contractor would add a layer of thin set concrete. We would add some additional insulation in a limited number of areas to improve the substrate grade to near flat, compensating for the undulations. The resulting near-flat surface allowed us to correctly install the fully tapered insulation. This ensured adequate water flow to the roof drains.

Height Requirements with Tapered Insulation

We noticed that the roof assembly thickness was too large to accommodate the door threshold onto the roof. It would jeopardize the proper fitting and performance of the over 600 individual pieces of pre-manufactured tapered insulation. We brought our findings to the architect and engineer early, allowing them to modify plans before construction began and eliminating potential delays.

Low Impact on Day-to-Day Operations

This building expansion differed from typical new construction in that we needed to cause as little disruption as possible to avoid impacting day-to-day building operations. We altered our usual approach and installed the fully adhered vapour barrier first. This ensured a watertight connection to the existing building as quickly as possible.

Safety of Residents, Families, and Employees during the Retirement Residence Roofing Project

For the duration of this retirement residence roofing project, the safety of our own workers, patients, medical staff, other employees, and their families was paramount. We adhered to the staging area provided to us by the contractor as well as all site-specific safety protocols.

The Elite Advantage: Accurate planning saves time and money for your retirement residence roofing project

Successful execution of complex roofing for a retirement residence project starts with careful planning and the ability to resolve technical challenges by working closely with the entire project team. During the pre-planning stages through project completion, the Elite team anticipated and helped resolve problems that otherwise may have derailed the project with costly delays, execution difficulties, and additional costs.

We are committed to getting the best results for our clients. Working closely with all parties throughout the construction process allowed us to confidently move forward and meet all project milestones, on schedule.